About the project

The construction of a designated building for the use of Yediot Ahronot national news group which is in close proximity to an active printing press, covering a total area of approx. 50,000 Sq.M. in the Rishon Lezion’s industrial area.

47K

47,000 Sq.M. building casing circumambient

50K

50,000 Sq.M. built area

40

40 Months of construction including finishes

12

12 Months of planning

The Challenge

  • Amalgamate the group’s internal organizational integration during a dynamic planning process
  • Establishment of a building adjacent to an active printing press that operates 24/7, without interruption to its’ regular operation
  • Plan to meet a tight budget and an uncompromising timetable
  • Construction of a fully finished building for the group’s use, including a multi-media studio and a newspaper press facility

Environmental Contribution

  • Transference of multiple buildings in central Israel to create a centralized facility
  • Coordination with the municipality of Rishon Lezion to arrange mass transit from the local train station to the workplace to reduce the use of private vehicles
  • Compliance with Green Building Standards before they were formally required